Regulatory Open Forum

 View Only
  • 1.  DSUR submission guideline

    Posted 25-Apr-2019 14:55
    Hi,

    I have a question in reference to the ICH guideline on the submission of DSURs to the applicable countries. As per ICH, "The DSUR should be submitted to all concerned regulatory authorities no later than 60 calendar days after the DSUR data lock point." However some countries have a 70 or 90 days guideline and some don't have a time period of DSUR submission.

    Now if we go by ICH guideline, if the submission is made after 60days, we consider them late and request a CAPA from the vendor doing the submission. However the vendor comes back saying that they are also not wrong as they are  following the local regulation of the country.

    We are in a fix and would like your inputs on this topic. Any guidance is highly appreciated!

    Thanks!





  • 2.  RE: DSUR submission guideline

    Posted 26-Apr-2019 03:47
    Hi Garima, 

    I was always reminded by local GCP inspectors from various European countries that national legislation always comes first. 

    I would say no need for CAPA for providing DSUR on time per local requirements, thus being compliant with local authorities. 

    However, if there was a safety reporting plan drafted between contractor/contractee which included global DSUR submission timeliness, and which did not state local requirements other than those described in ICH guidelines, this should be addressed formally as a process deviation. 

    Local requirements should be known, discussed and captured in reporting plan for this exact situation to be avoided. If you expect DSUR submission to occur within timelines which are more strict than those defined in local regulatory framework, I think that should have been explicitly stated. 

    There is this underlying challenge in communication pathways that often exists in contractor/contractee relations that might signal potential need to evaluate further this situation as well as reporting plans (if you don't have it in place, I strongly recommend drafting it as it will allow local differences to be captured and properly addressed), for occurances other than this might not end up with remaining compliant with local requirements.

    I hope this helps and looking forward for others' comments on this topic.

    Kind regards,

    ------------------------------
    Vladimir Vujovic
    Regulatory and Safety Manager
    Belgrade
    Serbia
    ------------------------------



  • 3.  RE: DSUR submission guideline

    Posted 26-Apr-2019 10:50
    Thank you so much Vladimir for your great suggestion. We have a flow plan/contractual agreement in place with the vendor stating that all submissions be made before 60days after the DLP as we state in our company SOPs which follow the ICH guidelines.
    However we are in the process of updating the SOPs and were looking to update the submission process to follow the national legislation of different countries.

    What I am figuring out with all these responses is we should consider following the local legislation of that country while doing DSUR submission.









  • 4.  RE: DSUR submission guideline

    This message was posted by a user wishing to remain anonymous
    Posted 26-Apr-2019 08:02
    This message was posted by a user wishing to remain anonymous

    ​Hi ~

    I would always follow the country guideline with regards to timelines, unless there is no country timeline in which case I would file according to the ICH recommendation (ie. no later than 60 days after DLP).

    Regards


  • 5.  RE: DSUR submission guideline

    Posted 26-Apr-2019 10:50
    Thank you for your response!





  • 6.  RE: DSUR submission guideline

    Posted 26-Apr-2019 09:09
    HI Garima,

    I think, you need to follow country specific timelines over ICH. Mostly requirements are different in country to country and ICH is offering standard timelines/requirements.

    Regards
    Hrishikesh

    ------------------------------
    Hrishikesh Dhongade MS
    Manager, Reg Ops
    Hyderabad
    India
    ------------------------------



  • 7.  RE: DSUR submission guideline

    Posted 26-Apr-2019 10:40
    Thank you Hrishikesh.





  • 8.  RE: DSUR submission guideline

    Posted 26-Apr-2019 10:14
    My only suggestion would be to ask for their procedure that governs DSUR submissions and then review to see if this is allowed per their procedure. If it is  and following their procedure, then not sure how you can ask for a CAPA as followed their procedure. Subsequently, if you not like their procedure , you would need to contractually address.

    ------------------------------
    Robert Blanks RAC
    VP, Regulatory Affairs and Quality Assurance
    [Ardelyx]
    Auburndale MA
    United States
    ------------------------------



  • 9.  RE: DSUR submission guideline

    Posted 26-Apr-2019 10:55
    Thank you Robert for your suggestion. Actually vendor follows the country regulation but we were giving importance to ICH guideline.

    My only concern is we do not know each and every country's regulation and DSUR submission policy, so how would we know if the vendor is making an correct submission.
    Is there any online site or reading material where I can find the DSUR submission guidelines for all the ICH and ROW countries?