  • 1.  Mechanism to amend IVDR Technical Documentation submitted to NB?

    This message was posted by a user wishing to remain anonymous
    Posted 05-Jan-2023 15:17
    This message was posted by a user wishing to remain anonymous

    FDA premarket submissions can be revised while being reviewed by FDA by submitting an amendment to the original submission. Is there a similar process in place under MDR/IVDR to update or revise the Technical Documentation while it is being reviewed by a Notified Body?

    Thank you


  • 2.  RE: Mechanism to amend IVDR Technical Documentation submitted to NB?

    Posted 05-Jan-2023 21:11
    Hello Anon,

    I haven't come across anything so would suggest to contact your scheme manager or reviewer. There is a Change notification process in place for making updates after NB approval of TF.

    BR,
    Jinali

    ------------------------------
    Jinali Bhavsar RAC
    Sr Regulatory Affairs Specialist II
    San Jose CA
    United States
    ------------------------------



  • 3.  RE: Mechanism to amend IVDR Technical Documentation submitted to NB?

    Posted 06-Jan-2023 07:25
    Yes, would suggest contacting the Notified Body directly, there all have different processes if changes need to made during an application currently in review.

    ------------------------------
    Richard Vincins ASQ-CQA, MTOPRA, RAC
    Vice President Global Regulatory Affairs
    ------------------------------